Blitz
Build Log:
Around the nation, more than 400 homes are being
built this week -- homes that will house more than 1,000 people. Check out
what we are doing here in Pinellas with the help of our sponsor, New
Millennial Homes.
Click on the items below to track our
progress!
Preconstruction
Day One - June 5
Day Two -
June 6
Day Three- June 7
Day Four- June
8
Last Day- June 9
|

Find out what it takes
to build a house in one week |
|
VISIT THE BLITZ
HOUSE &
SEE FOR YOURSELF
701 15th Ave. S., St. Petersburg |
|
Day
Five - June 9, 2006
Start Time: 5:30 am
End Time: 8:30 pm
Many thanks and congrats to all the
crews who helped to make this blitz a success.

6:45 am - Kitchen is almost done.
|

6:45 am - All the details are in
place. |

6:50 am - The sun starts to shine on
the house for the last build day. |

9:45 am - The last of the
baseboards |

10:15 - Landscaping |
|

3:45 pm - Part of the New Millennial
Crew |

6:30 pm - Ceremony to celebrate |

7 pm - Blessing the house |

7:20 pm - Burger time |

The Finished House!!!! |
|
BACK TO TOP |
|
Day Four - June 8,
2006
Start Time: 5:30 am
End Time:
10:30 pm
With crews ahead of schedule, this
house is almost done!

10:12 am - Flowers make the house a
home. |

10:14 am - A/C & electrical |

10:30 am - Almost done |

10:32 am - Fans quick dry the
baseboards |

10:32 am - Countertops & sinks |

10:45 am - Installing the porch rail |
BACK TO TOP
|
|
Day
Three - June 7, 2006
Start Time: 5:30 am
End Time:
10:30 pm
The inside is taking shape with
walls, paint and ... cabinets!

11:15 am - Paint time |

11:45 am - Painting the exterior |

12:00 pm - Is there more paint
on him or the walls? |

1:30 pm - Kitchen cabinets and paint |

2:07 pm - Mayor Rick Baker checks out
the house. |
|
| |
|
BACK TO TOP |
|
Day Two - June
5, 2006
Start Time: 7:00 am
End Time: 9:30 pm
With so much accomplished yesterday,
the crews are on track for drywall, roofing tiles and stucco. Drywall
typically takes 5 days. The Blitzers did it in one!

7:55 am - Drywall ready to go
|

9:00 am - Roof tiles in the works |

9:25 am - Stucco
|

9:30 am - Stucco
|

9:55 am - Drywall ceiling |

10:01 am - Two rooms take shape with
the drywall in. |

4:45 pm - Looking down the hall |

4:45 pm - You can almost picture the
living room. |

5:05 pm - The last of the stucco |

5:20 pm - Roof and stucco done! |
BACK TO TOP
|
Day One - June
5, 2006
Start Time: 6:00 am
End Time: 7:30 pm
Crews of workers swarmed the
property, laboring in the summer heat to accomplish the day's goals. As many
as 27 workers were inside the 1,150 square foot house at one time.

7:45 am - Starting on the trusses
|

7:53 am |

8:05 am - Working the crane
|

9:11 am - Trusses done
|

11:00 am - Windows in the works
|

11:22 am - Framework for interior
walls |

11:22 am - Check out that roof! |

12:30 pm - A 5-minute pizza
break before heading back on the roof |

2:25 pm - Getting wired
|

2:40 pm - Doing the heavy lifting
|

4:00 pm - Door out to the the front
porch |

5:15 - Looking at the insulation
|

6:00 pm - Readying the roof tiles
|
|
BACK TO TOP
|
Preconstruction
One of Pinellas Habitat's first block
construction homes, the Blitz house masonry shell was complete on Thursday,
June 1st to allow the masonry to set in preparation for the build.
BACK TO TOP
|
What does it
take to build a house in a week ... Dedication
Special thanks to all the
organizations and people who are making this project happen.
|
Project Sponsor |
Donors |
Participants |
|
New
Millennial
Homes |
CAPRI Engineering
Suncoast Roofing Supply
Tuscany Flooring LLC
Westco
Christopher T. Williams, Inc
Darnells’s Professional Janitorial, Inc
Brito’s Painting Inc
McLeod Electric Services LLC
Kenny’s A/C & Heating Svc., INC.
Plumbing Services by Badcock, Inc
Welsse Construction
Talmadge Drywall Inc
Daniel Insulation, Inc
Montrose Shelving
Rinker Material of Florida, Inc
Landscape Services, Inc
Tree Mart
Palifax Restoration |
Trane
84 Lumber
Christopher T. Williams, Inc
Darnells’s Professional Janitorial, Inc
DeVito Builders , Inc
Rich and Dave, Inc
Sims Crane & Equipment Co.
Owens Construction by Herbert Owens
Home Depot
Artistic Gutters and Siding, Inc
Ben’s Stucco & Stone, Inc
Security Termite Systems, Inc
Patrick McDonough, Inc
Unique Cabinet Designer’s Inc
Signs and Specialties
|
|